ERDWERK is proud to be part of EnergeÔ's first project, Vinzel. The drilling of the wells commenced as of 21 November 2022. The plan is to drill a production well to a depth of 2300 meters. This will take approximately 60 days, after which well tests will be completed which will determine the decision to drill a reinjection well. ERDWERK has been advising EnergeÔ on all aspects of geothermal planning since the project conception. For the drilling phase of the project ERDWERK is acting as the drilling manager coordinating all on-site activites.